KETRACO has energised the Sh8.4bn Isinya–Konza 400kV transmission line and substation, ensuring reliable power supply to Konza Technopolis. Breaking It Down NAIROBI, Kenya, Jun 14 – The Kenya Electricity Transmission Company (KETRACO) has energised the 400kV Isinya–Konza Transmission Line and the 400/132/66kV Konza Substation, marking a major milestone in Kenya’s efforts to strengthen national grid reliability and secure stable power supply fo
06/14/26 • 3 Views
KETRACO has energised the Sh8.4bn Isinya–Konza 400kV transmission line and substation, ensuring reliable power supply to Konza Technopolis.
📻 Breaking It Down
NAIROBI, Kenya, Jun 14 – The Kenya Electricity Transmission Company (KETRACO) has energised the 400kV Isinya–Konza Transmission Line and the 400/132/66kV Konza Substation, marking a major milestone in Kenya’s efforts to strengthen national grid reliability and secure stable power supply for Konza Technopolis.
The Sh8.4 billion project, jointly financed by the Export-Import Bank of China and the Government of Kenya, is designed to expand transmission capacity, improve grid stability, and meet rising electricity demand in the lower eastern region.
KETRACO said the commissioning of the infrastructure marks a key step in reinforcing the national transmission network while ensuring sufficient power supply for the expansion of Konza Technopolis and surrounding industrial, commercial and residential developments.
📌 What You Need to Know
The project consists of a 48-kilometre 400kV double-circuit transmission line, two 350MVA 400/132kV transformers, and two 75MVA 132/66kV transformers.
According to KETRACO Acting Managing Director Eng. Kipkemoi Kibias, the project is a strategic investment in Kenya’s long-term plan to build a resilient and modern electricity transmission system capable of supporting economic transformation.
“The successful energisation of the Isinya–Konza Transmission Line and Konza Substation strengthens the reliability of the national grid and guarantees quality power supply to Konza Technopolis and surrounding areas,” Kibias said.
He added that the project will play a key role in supporting industrialisation, attracting investment, and advancing Kenya’s Vision 2030 development agenda.
Kibias noted that the new infrastructure will improve electricity evacuation and distribution across Kajiado, Machakos and Makueni counties, while enhancing grid resilience through improved interconnectivity and alternative power routing.
The project is expected to significantly boost transmission capacity and expand access to stable electricity in the region, supporting growing demand from households, businesses and industries.